Flood-hit infrastructure rebuilt with emergency towers and alternate routes
Jammu, Sept 02: In the aftermath of the devastating rains and flash floods that struck Jammu on August 25 and 26, plunging the entire region into darkness, the Power Development Department (PDD) has managed to script a remarkable turnaround. Through round-the-clock coordination with multiple agencies, the department restored electricity supply to the region in record time, despite unprecedented damage to transmission and distribution networks.
The torrential downpour triggered landslides, flooded rivers, and overflowing nallahs that wreaked havoc on power infrastructure. Several transmission towers collapsed, foundations were washed away, and receiving stations were submerged. According to officials, the power load in Jammu dropped to 299 MW on August 26 against a normal demand of 1,050 MW, marking one of the sharpest declines in recent years.
Yet, restoration teams swung into action immediately. By isolating faulty elements and sourcing alternate supply routes, PDD managed to raise the load to 725 MW within 24 hours and to 960 MW by August 28 evening. Officials said this was achieved under the close supervision of Principal Secretary, PDD, H. Rajesh Prasad, with seamless coordination among JKPDC, JKPTCL, and JPDCL.
Senior government functionaries, including Lieutenant Governor Manoj Sinha, former Chief Minister Omar Abdullah, and Chief Secretary Atal Dulloo, monitored the restoration efforts closely, ensuring timely intervention and resource mobilization. Support from central PSUs such as NHPC and PGCIL further accelerated the drive.
Transmission lines posed the toughest challenge. Towers on the 132 kV Tawi crossing collapsed in a cascading chain, while key supply routes including the Hiranagar–Battal–Manwal and 220 kV Barn–Kishanpur lines were crippled, cutting off districts like Rajouri, Poonch, Reasi, and Kishtwar. Engineers battled difficult terrain, river crossings, and blocked roads to carry men and material, often resorting to head loads over steep hills.
In one instance, the JKPTCL team led by MD Rahilla Wani deployed an Emergency Restoration System (ERS) tower with support from PGCIL, restoring supply within 24 hours on a line that would normally take months to rebuild. Heavy-duty cranes and specialized equipment were pressed into service to re-string conductors along damaged stretches, while JPDCL simultaneously restored supply to hospitals, defence installations, AIIMS, GMC Jammu, and water supply systems on priority.
Distribution losses were equally alarming. Out of 1,349 feeders, barely 364 were functional by the evening of August 26, while nearly 19,000 transformers suffered damage. Despite this, JPDCL teams ensured that essential services were reconnected on the very first day.
The generation sector too bore the brunt. All JKSPDC hydroelectric projects in Jammu Division were forced into shutdown due to flooding, damaged roads, and heavy silt in rivers. Baglihar Hydroelectric Project, the region’s biggest at 900 MW, went offline on August 26. Through relentless efforts led by MD Rahul Yadav, the first unit was restored within 60 hours, and by August 29 all units were synchronized back to the grid.
Officials said while temporary restoration has been achieved, permanent rebuilding of damaged towers, poles, and substation equipment will require several months and stable weather conditions. Assessments for long-term repair and modernization are already underway.
The coordinated response of PDD, aided by central and state agencies, has drawn praise for averting a prolonged blackout. What began as a crisis that crippled the region’s lifelines has now been turned into a story of resilience and rapid recovery, with Jammu’s power sector demonstrating that even nature’s fury can be met with grit, planning, and teamwork.