Jammu, Jan 23: Incessant rainfall and heavy snowfall across Jammu Division triggered an unprecedented collapse in power demand, with Jammu Power Distribution Corporation Limited (JPDCL) recording a drastic low of just 140 MW at 4:00 AM—down from the normal average of 1150 MW.
Sustained restoration efforts have progressively lifted the running load to 891 MW, though full recovery remains challenging due to widespread disruptions from the extreme weather.
At the sub-transmission level, JPDCL restored 161 out of 181 critical 66/33 kV lines. Distribution networks show 740 of 1373 11 kV feeders operational, with priority work underway on remaining accessible feeders.
Restoration faces significant hurdles in snow-bound and rain-affected zones, particularly remote hilly areas. Severely impacted districts include Poonch, Rajouri, Kathua, Doda, Udhampur, Reasi, Ramban, Kishtwar, and Samba—especially higher reaches and interior pockets.
In Jammu district, heavy rainfall, gale-force winds, and uprooted trees inflicted widespread damage to high-tension (HT) and low-tension (LT) lines. Hilly terrains remain largely inaccessible, hampering damage assessment and repair timelines.
JPDCL deployed adequate manpower, machinery, and materials for comprehensive restoration. Close coordination with district administrations and partner agencies prioritizes vulnerable remote regions.
The corporation assures consumers of round-the-clock efforts to normalize supply, urging patience as weather conditions gradually improve and access routes clear.